Project Area is 30kms SW of Dacian Gold's Mt Morgans/Jubilee Project (Resource of 3.2M ounces in 2016)
Project area is 45kms WSW of the Wallaby and Granny Smith Gold Mines ( Resource of 6.5M ounces (31/12/2016)).
Project is 50kms WNW of Sunrise Dam ( Resource of 5.7 M ounces (31/12/2016)).
1800 line km at 50m line spacings of ground magnetic survey completed using two Gem GSMP35 Magnetometers (purchased new December 2016)
Ground survey was carried out by a geologist, ex Glencor (Murrin Murrin) previously ore body modelling at Murrin Murrin.
Interpretation of ground magnetics by Southern Geoscience Consultants delineating numerous targets and fault structures
Soil Geochemistry programmes by Goldfields Exploration produced targets in existing tenement area.
Synite Granites mapped in project area
Extensive old workings in the Betty & Lloyd /Windsor Well area including the Bendigo Group of Mines and other workings in older GMLs'.
Significant NW corridor of old workings and recent alluvial workings.
Redcastle tenements are immediately north of the historic Redcastle mining area and alluvial gold patches from scrape and detect methods are common where quartz reefs exist.